Field Instrumentation of Load of R/C Apartment under Construction according to Construction Stage

시공단계에 따른 RC공동주택의 동바리 하중 계측

  • 오재근 (대림산업(주) 건축연구지원팀) ;
  • 강수민 (대림산업(주) 건축연구지원팀) ;
  • 김욱종 (대림산업(주) 건축연구지원팀)
  • Published : 2008.04.24

Abstract

Recently, according to the increasement of high-rise building construction and domestic situation, requirements of rapid cycle construction are increasing. For more economical and rapid cycle construction, it is required to reduce formwork cost. So formwork have to be stripped as soon as possible. But as fresh concrete is loaded with construction load, it is likely that the structure will have problems with safety and serviceability. To reduce construction cycle economically, safety and serviceability of structure against construction load have to be considered. But as behavior of structure under construction is so complicated, behavior of structure has to be investigated according to construction stage. Therefore, through field instrumentation of apartment, behavior of structure under construction was analyzed.

최근 초고층 건축물뿐만 아니라 공동주택에서도 공기단축에 대한 요구가 증가하고 있다. 골조공기단축을 경제적으로 하기 위해서는 철근콘크리트 공사에서 40%정도를 차지하는 거푸집공사 비용을 줄이는 것이 중요하다. 경제적인 거푸집공사를 위해서는 적은 거푸집 벌수로 전용회수를 늘리고 동바리 지지층수를 줄이는 것이 유리하므로 강도발현 이전에 거푸집을 탈형하고 동바리를 제거한다. 그런데 시공단계의 진행에 따라 시공 중인 구조물에 시공하중이 가해지게 된다. 이러한 시공하중은 시공단계에 따라 변화하고 경우에 따라 과도한 시공하중이 아직 굳지 않은 콘크리트에 가해지므로 시공 중인 구조물의 안전성 및 사용성에 영향을 줄 수 있다. 보다 안전하고 경제적인 공기단축을 위해서는 이러한 시공 중인 구조물의 거동을 합리적으로 예측하여 적절한 가설계획을 세울 수 있어야 하고 이를 위해서는 우선 시공단계에 따른 구조물의 거동이 어떻게 변하는지를 조사해야 한다. 따라서 본 연구에서는 시공 중인 공동주택 가운데 바닥면적이 넓은 1세대를 선정하고 현장계측을 수행하였다. 동바리 하중 변화를 측정하기 위하여 동바리의 하부에 로드셀을 설치하였고 10층 거푸집 설치 단계부터 11층 동바리 제거단계까지의 시공단계의 진행에 따라 동바리의 하중변화를 계측하고 이를 분석하였다.

Keywords