Estimation of Optimal Hydro-Power Supply Amount of Yongdam Multipurpose Dam for the Contract on the Free-Competition Market

자유경쟁 시장 내에서 용담다목적댐 발전소의 최적 계약가능 공급량 평가

  • 유주환 (영동대학교 건설계열 토목환경공학과)
  • Published : 2005.01.01

Abstract

Nowaday the amount of water resource to generate the hydro-power energy has decreased as that of the water supply has increased. In case that the national market of the energy will be in free competition, the energy producer need to suggest the amount of the optimal supply with the hydrological reliability for a deal. In this study the optimal reservoir operation was performed by the linear programming and the optimal reliabilities of inflows and the power supply were obtained by the one dimensional search technique to estimate the energy with the optimal inflow reliability which the power system of the Yongdam multipurpose dam in Geum river can produce. And the main results were presented.

요즘 다목적댐의 수력발전을 일으킬 수 있는 수자원은 용수공급이 증가함에 따라서 점점 감소하고 있는 형편이다. 한편 국내 수력 발전량의 거래가 다자간의 시장경제 체제로 형성될 경우, 수력에너지 생산자는 최적 공급량과 공급의 수문학적 신뢰도 수준을 제시해야 한다. 이에 본 연구에서는 금강 수계 내 위치한 용담다목적댐의 수력 발전소에서 공급가능한 발전량과 공급 신뢰도를 평가하기 위하여 저수지 조작 기법으로 선형계획법을 적용하였고 1차원 조사법을 이용하여 유입량의 신뢰도와 수력 발전 공급량의 최적치를 결정하였고 그 주요 결과를 제시하였다.

Keywords

References

  1. 건설부 (1989). 전주권 2단계지역 개발사업 타당성조사 용담수원개발 방안조사 보고서
  2. 권오헌, 유주환 (1993). '저수지 유입량의 신뢰도를 고려한 최적계약 전력량의 결정.' 대한토목학회논문집, 제13권, 제2호, pp. 141-149
  3. 김주철, 유주환, 김재환, 정관수 (2002). '금강수계 다목적 저수지 유입량의 신뢰도 분석.' 한국수자원학회학술발표논문집, pp. 733-738
  4. 안태진, 류희정, 박정웅 (1999). '최적화기법을 이용한 기존 농업용 저수지에서의 부존 수력발전량 추정.' 한국수자원학회논문집, 제32권, 제3호, pp. 281-289
  5. 유주환 (1999). '금강수계 수위-유량곡선 개발 및 적용.' 대한토목학회논문집, 제19권, 제II-6호, pp. 665-675
  6. 유주환, 김재한, 정관수 (1999). '한강수계 복합저수지 시스템의 최적 수력발전운영을 위한 Linear Tracking의 적용.' 한국수자원학회논문집, 제32권, 제5호, pp. 579-591
  7. 유주환, 박창근, 조효섭 (2001). '평화의 댐 홍수지체 효과에 따른 화천댐 계통 이수 능력의 증대에 대한 검정.' 한국수자원학회논문집, 제34권, 제6호, pp. 617-625
  8. 한국건설기술연구원 (1996). 수자원장기종합계획(1997-2001) 부록 수자원자료집
  9. 한국수자원공사 (1990). 용담다목적댐 타당성조사보고서, 건설부
  10. 한국수자원공사 (1991). 용담다목적댐 건설사업 실시 설계 보고서, 건설부
  11. 한국수자원공사 (1995-2000). 용담다목적댐 건설 업무 자료집, 용담댐건설단
  12. Askew, A.J. (1974a). 'Optimum reservoir operating policies and the imposition of a reliability constraint.' Water Resources Research, Vol. 10, No. 1, pp. 51-56 https://doi.org/10.1029/WR010i001p00051
  13. Askew, A.J. (1974b). 'Chance-constrained dynamic programming and the optimization of water resource systems.' Water Resources Research, Vol. 10, No.6, pp. 1099-1106 https://doi.org/10.1029/WR010i006p01099
  14. Askew, A.J. (1975). 'Use of risk premium in chance-constrained dynamic porgramming.' Water Resources Research, Vol. 11, No.6, pp. 862-866 https://doi.org/10.1029/WR011i006p00862
  15. Colorni, A. and Fronza, G. (1976). 'Reservoir management via reliability programming.' Water Resources Research, Vol. 12, No. 1, pp. 85-88 https://doi.org/10.1029/WR012i001p00085
  16. Lee, Han-Lin and Brill, E.D. (1987). Reliability of reservoir operation under hydrologic uncertainty. Water Resources Center, University of Illinois at Urbana Champaign, Research Report, No. 207
  17. ReVelle, C., Joeres, E. and Kirby, W. (1969). 'The linear decision rule in reservoir management and design, 1. development of the stochastic model.' Water Resources Research, Vol. 5, No. 4, pp. 767-777 https://doi.org/10.1029/WR005i004p00767
  18. Simonovic, S.P. and Manrino, M.A. (1980). 'Reliability programing in reservoir management 1. single multipurpose reservoir.' Water Resources Research, Vol. 16, No. 5, pp. 844-848 https://doi.org/10.1029/WR016i005p00844

Cited by

  1. Maximization of hydropower generation through the application of a linear programming model vol.376, pp.1-2, 2009, https://doi.org/10.1016/j.jhydrol.2009.07.026