Business Process Model for Progress Phase of Design-Build Project

설계시공일괄방식 사업의 진행단계별 업무프로세스 모델

  • Published : 2009.06.30

Abstract

In public project market, design-build projects have been increased because of market trend change which enables technical competition. In this condition, its importance is also getting important. Generally, life cycle of design-build project consists of planning, preliminary design, procurement, contract, detail design, start of construction, construction, end of construction, and evaluation. From contractor's viewpoint, it has problems such as difficulties in project management and information sharing because of frequent change of charged division. To solve these problems, it is desirable to change from function-based management system to process-based management system. The purpose of this study is to develop management process model for design-build project by progress phases. This study analyzed main conflicts and decision making factors of each stage in design-build projects, then systemized management subjects' responsibilities and management points' change. And also this study defined the key information that is the key point by project characteristics and progress phases. Based on this analysis, this study did business process modeling from planning stage to construction design check stage. At last, we proposed the way to manage business process by design-build project progress.

최근 정부 공사를 중심으로 기술경쟁이 가능한 설계시공일괄 입찰방식이 확대 적용되고 있는 추세이며 이러한 시장의 변화에 따라서 그 중요성이 더욱 증가할 것으로 예상된다. 일반적으로 설계시공일괄방식의 단위 건설사업 생애주기는 기획, 기본 설계, 입찰, 계약, 상세설계, 착공, 시공, 준공, 평가의 진행단계를 가지게 된다. 계약자의 측면에서 주무부서의 잦은 변화로 효율적인 프로젝트 관리와 일관성 있는 정보의 공유가 어려워지는 문제점이 드러나고 있다. 이러한 문제점을 해결하기 위해 기존의 주무부서에 따른 기능 중심의 관리 체계에서, 프로젝트 중심의 관리 프로세스 체계로의 전환이 필요하다. 본 연구에서는 이러한 필요성에 따라 단위 프로젝트의 진행단계별 관리 프로세스 모델 개발을 목적으로 하였다. 이를 위해서 설계시공일괄방식의 진행단계별 주요 관리 쟁점과 의사결정 사항, 업무 분석을 하였고, 진행단계별 관리 주제의 책임 및 권한과 주요 관리 포인트의 변화를 분석하여 체계화 하였다. 프로젝트 특성별 및 진행단계별 연결고리가 되는 핵심 정보를 정의 하고 정보의 흐름을 분석하였으며, 이를 바탕으로 최종적으로 발주계획 수립 단계부터 실시설계 심의 단계까지의 업무 프로세스를 모델링하고 각 수행 주체별 업무프로세스를 모델링 하여 단위 프로젝트의 진행단계별 관리 프로세스 모델을 개발하였다.

Keywords

References

  1. Ahmet Oztas, Risk Analysis in Fixed-Price Design-Build Construcion Projects, Elsevier Journal, 2003 https://doi.org/10.1016/j.buildenv.2003.08.018
  2. Albert P.C. Chan, Design-Build Projects Success Factors, Journal of Construction Engineering and Management, 2001 https://doi.org/10.1061/(ASCE)0733-9364(2001)127:2(93)
  3. California Department of Education, Design-Build Project Guidelines. Edition, California department of education, 2002
  4. DNA, The Design-Build Process, 1994
  5. Florence Yeari & Yng Ling, How Project Manager Better Control the Performance of Design-Build Projects, Elsevier Journals, 2003 https://doi.org/10.1016/j.ijproman.2003.09.003
  6. Fredrickson, K., 'Design Guidelines for Design-Build Projects', Journal of Management in Engineering, Vol.14, No.1, pp.77-80 https://doi.org/10.1061/(ASCE)0742-597X(1998)14:1(77)
  7. Jack Rizzo. Design/build alternative: A contracting method. Journal of management in engineering. 1998 https://doi.org/10.1061/(ASCE)0742-597X(1998)14:6(44)
  8. Keith R. Molenaar, Public-Sector Design/Build Evolution and Performance, Journal of Construction Engineering and Management, 1999 https://doi.org/10.1061/(ASCE)0742-597X(1999)15:2(54)
  9. Washington State Department of Transportation, Guidebook for Design-Build Highway Project Development, 2001
  10. 국토해양부(구 건설교통부), 턴키.대안입찰제도 업무요령, 2003. 8
  11. 김병천, 국내 Design-Build 공사계약일반조건 개발 방안, 중앙대학교 건설대학원 석사학위 논문, 1999
  12. 김정훈, 일반체계이론을 적용한 선택적 설계시공일괄방 식 체계에 관한 연구, 대한건축학회논문집 구조계, 19권 10호, 2003
  13. 김태삼, 국내 공공부문 디자인 빌드 계약의 프로세스모델 개발에관한 연구, 시립대학교 석사학위논문, 2001
  14. 이교선, 턴키 입찰제도의 장기전략 방향, 턴키 입찰제도의 장기발전전략 마련을 위한 공청회, 2001.5
  15. 이상호, 건축공사 턴키 발주방식의 개선 방안, 대한건축학회지, 2003
  16. 정준영, 김예상, 턴키사업 추진단계 관리업무의 체계화를위한 문제점 및 장애 요인분석에 관한 연구, 대한건축학논문집 구조계, 17권 9호, 2001
  17. 정준영, 턴키프로젝트(Turn-Key Projects) 기획관리모델 관한 연구, 성균관대학교 석사학위논문, 2001
  18. 한국건설경제협의회, 턴키공사의 유용성에 관한 고찰, 2003
  19. 한국건설관리학회, 턴키 프로젝트 사례분석을 통한 실시설계의 프로세스 모델에 관한 연구, 2003