DOI QR코드

DOI QR Code

Characteristics of Subsidence of a Road During the New Tubular Roof Construction Around a Shallow Tunnel

저심도 터널주변의 NTR보강 중 발생한 도로면 침하의 특성

  • Kim, Cheehwan (Department of Construction System Engineering, Woosuk University)
  • 김치환 (우석대학교 건설시스템공학과)
  • Received : 2018.11.27
  • Accepted : 2018.12.16
  • Published : 2018.12.31

Abstract

The NTR(New Tubular Roof) method was used to secure the stability of the tunnel and minimize the subsidence of the road. The tunnel was constructed at about 7.5 meters deep below the highway. with a width of about 21 meters. Following the NTR method, 13 steel pipes with a diameter of 2.3 meters were digged and pushed in longitudinally along the tunnel profile and cut out sides of pipes to connect to adjacent pipes, then filled the inside of pipes and the connected space between pipes with concrete to complete the lining of the tunnel to be excavated. As the steel pipes were digged in sequentially, the area of relaxation was connected to each other and behaves like a gradually widening tunnel. When the steel pipes were digged in to the widest points of the tunnel, the settlement rate of the road surface was increasing to the maximum as 2.2 mm and the total settlement until the lining construction was approximately 7.7 mm. After that, by excavating a tunnel inside the pre-installed lining, an additional settlement of about 4.3 mm was occurred, resulting in the total settlement of about 11.8 mm after completing of tunnel construction.

고속도로면으로 부터 심도는 약 7.5 m로 얕으나 너비가 약 21 m로 넓은 터널의 안정성을 확보하고 도로면의 침하를 최소화하기 위하여 NTR(New Tubular Roof)공법을 보조공법으로 이용하였다. 이 방법에 따라 터널 굴착예정선 둘레에 직경 2.3 m의 강관 13개를 종방향으로 압입하고 강관측벽을 뚫어 서로 연결한 후 강관내부와 연결공간을 콘크리트로 채워 라이닝을 먼저 만들었고 라이닝 내부 지반을 굴착하여 터널을 완성하였다. 여러 개의 강관을 순차적으로 압입함에 따라 이완영역이 서로 연결되면서 폭이 점차 넓어지는 공동으로 거동하여 침하증분이 커졌고 터널 폭이 가장 넓은 곳에 강관을 압입할 때 도로면 침하증분은 약 2.2 mm로 최대였으며 라이닝 시공 때 까지의 총침하는 약 7.7 mm이었다. 그리고 폭이 넓은 라이닝 내부 터널을 굴착하면서 약 4.3 mm의 침하가 추가로 발생하면서 시공종료 후 총침하는 약 11.8 mm가 되었다.

Keywords

OBGHBQ_2018_v28n6_620_f0001.png 이미지

Fig. 1. Site location and plan of tunnel

OBGHBQ_2018_v28n6_620_f0002.png 이미지

Fig. 2. Geological condition shown inside pipes

OBGHBQ_2018_v28n6_620_f0003.png 이미지

Fig. 3. Cross section and reinforcements around tunnel

OBGHBQ_2018_v28n6_620_f0004.png 이미지

Fig. 4. Sequential steel pipe jacking process

OBGHBQ_2018_v28n6_620_f0005.png 이미지

Fig. 5. Sequences of jacking steel pipes

OBGHBQ_2018_v28n6_620_f0006.png 이미지

Fig. 6. Plan for measurement of road settlement

OBGHBQ_2018_v28n6_620_f0007.png 이미지

Fig. 7. Three dimensional subsidence surface

OBGHBQ_2018_v28n6_620_f0008.png 이미지

Fig. 8. Cross sectional subsidence curve after sequence of pipe jackings and tunnel excavations

OBGHBQ_2018_v28n6_620_f0009.png 이미지

Fig. 9. Longitudinal subsidence curve after stage 7 of pipe jacking and stage 9 of tunnel excavation

OBGHBQ_2018_v28n6_620_f0010.png 이미지

Fig. 10. Total and incremental subsidence at stages

OBGHBQ_2018_v28n6_620_f0011.png 이미지

Fig. 11. Relation between total and incremental subsidence and distance of pipes at the same stage

OBGHBQ_2018_v28n6_620_f0012.png 이미지

Fig. 12. Relation incremental subsidence and depth over width of pipes coverage

References

  1. 김상수 역, 1992, 도시터널의 NATM공법, 창우출판.
  2. 서울특별시도시기반시설본부, 2014a, 하남선(5호선연장) 지반조사보고서.
  3. 서울특별시도시기반시설본부, 2014b, 하남선(5호선연장) 기본 및 실시설계보고서.
  4. B. M. New and K. H. Bowers, 1994, Ground movement model validation at the Heathrow Express trial tunnel, Tunnelling94, Tunnelling-Int. Sympo., pp.301-332.
  5. Kim Cheehwan, 2013a, Measurement of tunnel arch settlements ahead of and behind the tunnel face using a horizontal inclinometer and settlement pins, Tunnel & Underground Space, Journal of Korean Society for Rock Mechanics, Vol. 23, No. 2, pp. 120-129.
  6. Kim Cheehwan, 2013b, Characteristics of Subsidence above a Shallow Tunnel Excavated in Weathered Rock Mass, Tunnel & Underground Space, Journal of Korean Society for Rock Mechanics, Vol. 23, No. 5, pp. 337-346.
  7. Kim Cheehwan, 2015, Case study of a shallow tunnelling through complex strata of sand-gravel and rock mass, Tunnel & Underground Space, Journal of Korean Society for Rock Mechanics, Vol. 25, No. 3, pp. 244-254.
  8. Matworks, 2016, Matlab R2016a.