Spatiotemporal chronographical modeling of procurement and material flow for building projects

  • Francis, Adel (Construction Engineering Department, Ecole de technologie superieure, Quebec University) ;
  • Miresco, Edmond (Construction Engineering Department, Ecole de technologie superieure, Quebec University) ;
  • Le Meur, Erwan (Ecole Nationale Superieure d'Architecture de Paris-Belleville, Universite de Paris Est)
  • Received : 2018.09.30
  • Accepted : 2019.02.13
  • Published : 2019.04.25

Abstract

Planning and management building projects should tackle the coordination of works and the management of limited spaces, traffic and supplies. Activities cannot be performed without the resources available and resources cannot be used beyond the capacity of workplaces. Otherwise, workspace congestion will negatively affect the flow of works. Better on-site management allows for substantial productivity improvements and cost savings. The procurement system should be able to manage a wider variety of materials and products of the required quality in order to have less stock, in less time, using less space, with less investment and avoiding multiple storage stations. The objective of this paper is to demonstrate the advantages of using the Chronographic modeling, by combining spatiotemporal technical scheduling with the 4D simulations, the Last Planner System and the Takt-time when modeling the construction of building projects. This paper work toward the aforementioned goal by examining the impact that material flow has on site occupancy. The proposed spatiotemporal model promotes efficient site use, defines optimal site-occupancy and workforce-rotation rates, minimizes intermediate stocks, and ensures a suitable procurement process. This paper study the material flow on the site and consider horizontal and vertical paths, traffic flows and appropriate means of transportation to ensure fluidity and safety. This paper contributes to the existing body of knowledge by linking execution and supply to the spatial and temporal aspects. The methodology compare the performance and procurement processes for the proposed Chronographic model with the Gantt-Precedence diagram. Two examples are presented to demonstrate the benefits of the proposed model and to validate the related concepts. This validation is designed to test the model's graphical ability to simulate construction and procurement.

Keywords

References

  1. Ala-Risku, T. and Karkkainen, M. (2006), "Material delivery problems in construction projects: A possible solution", J. Production Economics, 104(1), 19-29. https://doi.org/10.1016/j.ijpe.2004.12.027
  2. Bell, L.C. and Stukhart, G. (1987), "Costs and benefits of materials management systems", J. Construct. Eng. Manag., 113(2), 222-234. https://doi.org/10.1061/(ASCE)0733-9364(1987)113:2(222)
  3. Bertelsen, S. and Nielsen, J. (1997), "Just-in-time logistics in the supply of building materials", Proceedings of the 1st International Conference on Construction Industry Development, Singapore, December.
  4. Bertin, J. (2005), Semiologie graphique, les diagrammes - les reseaux - les cartes (4th Ed.), EHESS, Paris.
  5. Chavada, R.D., Kassem, M., Dawood, N.N. and Naji, K.K. (2012), "A framework for construction workspace management: A serious game engine approach", Proceedings of the 2012 ASCE International Conference on Computing in Civil Engineering, June.
  6. Fisk, R.E. and Reynolds, W.D. (2013), Construction Projects Administration (10th Ed.), Pearson Education, London, United Kingdom.
  7. Francis, A. (2013), "The chronographical approach for construction project modelling", Proceedings of the Institution of Civil Engineers-Management, Procurement and Law, 166(4), 188-204. https://doi.org/10.1680/mpal.12.00009
  8. Francis, A. (2016), "A Chronographic protocol for modelling construction projects", Proceedings of the Institution of Civil Engineers-Management, Procurement and Law, 169(4), 168-177. https://doi.org/10.1680/jmapl.15.00039
  9. Francis, A. (2017), "Simulating uncertainties in construction projects with chronographical scheduling logic", J. Construct. Eng. Manag., 143(1), 1-14. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001212
  10. Francis, A. and Miresco, E.T. (2000), "Decision support for project management using a chronographic approach", Proceedings of the 2nd International Conference on Decision Making in Urban and Civil Engineering, Lyon, France, November.
  11. Francis, A. and Miresco, E.T. (2002), "Decision support for project management using a chronographic approach", J. Decision Syst., 11(3-4), 383-404. https://doi.org/10.3166/jds.11.383-404
  12. Francis, A. and Miresco, E.T. (2006), "A chronographic method for construction project planning", Canadian J. Civil Eng., 33(12), 1547-1557 https://doi.org/10.1139/l06-148
  13. Francis, A., Bibai, J. and Miresco, E.T. (2013), "Simulation of scheduling logic using dynamic functions", Proceedings of the Institution of Civil Engineers-Management, Procurement and Law, 166(3), 145-158. https://doi.org/10.1680/mpal.11.00049
  14. Francis, A., Le Meur, E. and Miresco, E. (2018), "Space planning of material flow for building projects: The Chronographical modelling concept", Proceedings of the 17th International Conference on Computing in Civil and Building Engineering, ISCCBE, Tampere, Finland, July.
  15. Frandson, A. and Tommelein, I.D. (2014), "Development of a Takt-time plan: A case study", Proceedings of the Construction Research Congress, Atlanta, GA, May.
  16. Horman, M.J. and Thomas, H.R. (2005), "Role of inventory buffers in construction labor performance", J. Construct. Eng. Manag., 131(7), 834. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:7(834)
  17. Keim, D.A. (2002), "Information visualization and visual data mining", IEEE Transactions on Visualization and Computer Graphics, 7(1), 100-107.
  18. Ng, S.T., Shi, J. and Fang, Y. (2009), "Enhancing the logistics of construction materials through activity-based simulation approach", Eng., Construct. Architect. Manag., 16(3), 224-237. https://doi.org/10.1108/09699980910951645
  19. Ning, X., Lam, K. and Lam. M.C. (2010), "Dynamic construction site layout planning using max-min ant system", Automat. Construct., 19(1), 55-65. https://doi.org/10.1016/j.autcon.2009.09.002
  20. Pheng, L.S. and Chuan. C.J. (2001), "Just-in-time management of precast concrete components", J. Construct. Eng. Manag., 127(6), 494-501. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:6(494)
  21. Riley, D.R. and Sanvido, V.E. (1995), "Patterns of construction-space use in multistory buildings", J. Construct. Eng. Manag., 121(4), 464-473. https://doi.org/10.1061/(ASCE)0733-9364(1995)121:4(464)
  22. Riley, D.R. and Sanvido, V.E. (1997), "Space planning method for multistory building construction", J. Construct. Eng. Manag., 123(2), 171-180. https://doi.org/10.1061/(ASCE)0733-9364(1997)123:2(171)
  23. Rischmoller, L., Fisher, M., Fox, R. and Alarcon, L. (2001), "4D planning and scheduling (4D-PS): Grounding construction IT research in industry practice, construction information technology", Proceedings of CIB W78 International Conference-IT in Construction in Africa, Mpumalanga, South Africa, May.
  24. Su, X. and Cai, H. (2014), "Life cycle approach to construction workspace modeling and planning", J. Construct. Eng. Manag., 140(7), 1-12.
  25. Su, X. L., Zhang, A.R. and Cai, H. (2012), "GIS-based buffering for construction workspace management, Construction Research Congress, West Lafayette, Indiana, 1252-1261.
  26. Thomas, H.R., Riley, D. and Messner, J.I. (2005), "Fundamental principles of site material management", J. Construct. Eng. Manag., 131(7), 808. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:7(808)
  27. Tufte, E.R. (1983), The Visual Display of Quantitative Information, Graphics Press, Cheshire, CT, U.S.A.
  28. Winch, G.M. and North, S. (2006), "Critical space analysis", J. Construct. Eng. Manag., 132(5), 473-481. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:5(473)
  29. Zouein, P.P. and Tommelein, I.D. (2001), "Improvement algorithm for limited space scheduling". J. Construct. Eng. Manag., 127(2), 116-124. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:2(116)

Cited by

  1. Spatiotemporal Planning of Construction Projects: A Literature Review and Assessment of the State of the Art vol.6, 2019, https://doi.org/10.3389/fbuil.2020.00128
  2. A semi-automated method for integrating textural and material data into as-built BIM using TIS vol.5, pp.2, 2019, https://doi.org/10.12989/acd.2020.5.2.127
  3. Barriers to BIM Adoption in Brazil vol.7, 2019, https://doi.org/10.3389/fbuil.2021.520154